Construction of rail overbridge at Kulavanigarpuram level crossing likely to start this year

The much-awaited rail overbridge at Kulavanigarpuram manned level crossing may get realised in near future as District Collector Anand Mohan inspected the spot on Thursday after proposal for constructing a ‘Y’-shaped ROB at this spot on an outlay of ₹120 crore has been submitted

The Hindu3 phút đọc

Construction of rail overbridge at Kulavanigarpuram level crossing likely to start this year

The much-awaited rail overbridge at Kulavanigarpuram manned level crossing may get realised in near future as District Collector Anand Mohan inspected the spot on Thursday after proposal for constructing a ‘Y’-shaped ROB at this spot on an outlay of ₹120 crore has been submitted for administrative sanction.Seed for constructing ROB at Kulavanigarpuram manned level crossing, a much-needed project, was sown in 2007 as this level crossing near Palayamkottai Central Prison on the busy Thiruvananthapuram Highway is closed 16 times a day causing severe traffic jam along this road for more than a kilometre every time. As vehicles, including ambulances rushing to Tirunelveli Medical College Hospital get trapped in this traffic snarl every time, at least 15 minutes are required for normalcy to return, which poses serious threat to the life of critically ill patients.

Minister T. P. M.

Mohideen Khan, who was representing Palayamkottai Assembly constituency, took the steps for constructing this ROB. Since the pillars to be erected on both sides of this bridge threatened private properties on both sides of the Palayamkottai – Kulavanigarpuram Railway Gate stretch, they obtained interim stay from the Madurai Bench of Madras High Court.After prolonged legal battle, the Court gave green signal for the ROB by clearing interim stays to pave way for giving compensation to the land losers.

Moreover, the soil tests have also been completed and these test results have been submitted to the Chief Engineer of Department of Highways for the mandatory approval.Even after the then Chief Minister M. K.

Stalin announced during his visit to Tirunelveli in September 2022 that the ROB would be built within a year, no step was taken by the Department of Highways to translate this promise into action.The inspection by the District Collector has now rekindled hopes for finding everlasting solution to the excruciating traffic jam at this spot whenever the manned level crossing is closed.“The proposed ‘Y’-shaped ROB will ensure unhindered movement of vehicles coming from Palayamkottai bus-stand to the new bus stand and Melapalayam and vice-versa even when the Kulavanigarpuram manned level crossing is closed.

A sum of ₹17.73 crore has been received to be given as compensation to the land-losers and 90% of this task has been completed. So, the disbursal of compensation will be completed before August-end,” Mr.

Anand Mohan said after inspection of the site for the ROB on Thursday.The Collector also reviewed the progress of the work on 32-Km-long Tirunelveli west bypass road, which is being implemented at a cost of ₹500 crore to decongest traffic within Tirunelveli and Palayamkottai by connecting the Tirunelveli – Kanniyakumari 4-lane national highway at Konganthanparai intersection near IRT Polytechnic and Thazhaiyoothu via Tharuvai, Suthamalli, Abhishekapatti and Rastha.In other words, vehicles, particularly heavy vehicles proceeding to Tenkasi or Kerala from Nagercoil, Thoothukudi and Kovilpatti can take this road instead of traversing the highly cramped Tirunelveli Junction and Tirunelveli Town roads.

In the first phase between Konganthaanpaarai intersection, road has been laid for 12 Km. However, construction of two elevated bridges, two small bridges and 44 culverts is going on in this stretch.In the second phase, 98% of land acquisition for laying road for 20 Km has been completed as ₹80 crore is being given as compensation to the land-losers.

Hence, work on this stretch is also likely to start shortly. Published - July 30, 2026 06:16 pm IST Read Comments Copy link Email Facebook Twitter Telegram LinkedIn WhatsApp Reddit READ LATER SEE ALL Remove

Nguồn: The Hindu

Đọc thêm từ Thế giới

“문자 속 ‘정 선배’ 정진석 맞냐”추궁에 정몽규 “프라이버시”
Thế giới

“문자 속 ‘정 선배’ 정진석 맞냐”추궁에 정몽규 “프라이버시”

본문정치정치일반“문자 속 ‘정 선배’ 정진석 맞냐”추궁에 정몽규 “프라이버시”고경주,조희연기자수정 2026-07-30 22:57펼침0:00Your browser does not support theaudio element.구글 선호 매체 등록국회 문화체육관광위원회 위원인 윤용근 국민의힘 의원이 30일 국회에서 열린 본회의에서 대한축구협회관련 청문회에 증인으로 출석한 정몽규 전 대한축구협회 회장에게 받은 문자를 확인하고 있다. 서울신문 제공 광고 윤용근 국민의힘 의원이 30일 국회 문화체육관광위원회

The Hankyoreh